Check actual product dimensions before converting area into an order.
Separate nominal face calculations, allowance and supplier packaging for wall units and tiles.
Record the product assumption
A wall-unit count depends on its measurement module. Keep the chosen face dimensions beside the wall reference and openings. Do not treat a nominal example as a universal Kenyan stone or concrete-block size.
Check the block example
A 10 × 3 m wall has 30 m² gross area. Deducting 4 m² of openings gives 26 m². The nominal 0.4 × 0.2 m face is 0.08 m², giving 325 units before allowance. With the selected 5% and upward rounding, the result is 342.
At illustrative KES65 each, the unit subtotal is KES22,230. Confirm actual dimensions, joints, special units, cuts and wall details. Mortar, grout, reinforcement, lintels, finishes, labour, delivery and tax are separate.
Compare the tile purchase
A 6 × 5 m floor measures 30 m². With a chosen 10% allowance, the planning area is 33 m². At 1.44 m² coverage per box, 22.92 boxes round up to 23, covering 33.12 m². At illustrative KES1,400 per box, the tile subtotal is KES32,200.
Adhesive, grout, trims, preparation, installation, transport and tax are outside that subtotal. Review cuts, layout and agreed spare material before accepting an allowance.
Check the supplier’s commercial pack
- Confirm the price unit and actual coverage.
- Separate additional pack rounding from the demo quantity.
- Record unloading and storage responsibility.
- Keep selections and availability questions visible.
- Recalculate after changing the product.
The schedule explains a proposed purchase; it does not reserve stock or establish product suitability. Agree actual specifications and supply terms directly before ordering.